1
This section gives a general introduction to the principal civil engineering structures — buildings, bridges, dams, weirs, tunnels and roads — and covers stakeout: its meaning, principles and survey techniques.
2
Buildings • Components: the substructure (foundation and plinth, transferring the load to the ground) and the superstructure (columns, beams, walls, slabs, staircase, roof, doors and windows, finishes). • Foundations: shallow — isolated/spread footing, combined footing, strip footing, raft/mat; deep — pile, pier and well/caisson foundation, used where the bearing stratum is deep or the load is heavy.
3
Selection depends on the safe bearing capacity, the depth of good ground, the water table and the loading. • Structural systems: load-bearing masonry (brick or stone walls carrying the load — common in Nepali housing), RCC framed structures (columns, beams and slabs), and steel or composite frames.
4
Loads are dead, live (imposed), wind, seismic, snow and temperature effects. • Seismic design matters in Nepal: the Nepal National Building Code (NBC) and the Building Act govern design, with mandatory rules of thumb for ordinary houses; symmetry, continuity, adequate ductile detailing and good construction quality determine performance.
5
Setting out requires precise right angles and diagonals, level plinths and plumb columns. • Survey inputs: site topographic survey and levels, setting out of the grid of column centres, foundation and plinth levels, verticality checks of columns and lift shafts, floor levels, and settlement monitoring of large buildings.
6
Bridges • Components: superstructure (deck, girders, trusses, cables, bearings) and substructure (piers, abutments, wing walls, foundations), plus approaches, river training and protection works. • Types: beam/girder (RCC, steel, prestressed), slab and box girder; arch; truss; cantilever; cable-stayed; suspension — the last being the characteristic type for long spans and for Nepal's many trail and suspension footbridges; and culverts for very small spans. • Terms: span (clear and effective), waterway, afflux, freeboard, vertical clearance above HFL, scour depth and skew angle. • Survey inputs: site selection and the bridge axis, cross-sections and HFL, sounding and scour survey, setting out of piers and abutments by intersection, precise levels for bearings and deck, and post-construction monitoring of piers.
7
Dams and Weirs • Dam — a barrier across a river creating a reservoir for storage.
8
Types by material: earthfill and rockfill embankment dams (the commonest, flexible, needing a wide base and spillway away from the body), concrete gravity (resists by weight), arch (transfers thrust to the abutments in a narrow gorge), buttress; and by purpose: storage, diversion, detention. • Appurtenances: spillway (passes flood safely — the single most critical safety element), energy dissipator/stilling basin, outlet works and sluices, gallery, cut-off and grout curtain against seepage, and instrumentation. • Weir — a low barrier that raises and diverts water without significant storage, used at the headworks of irrigation and run-of-river hydropower schemes; a barrage is a gated structure giving fuller control of levels.
9
Nepal's hydropower is predominantly run-of-river with a weir and side intake. • Survey inputs: catchment and reservoir survey with elevation-area-capacity curves, detailed foundation topography, precise setting out of the axis and of the spillway crest level, borrow-area and quantity survey, and deformation monitoring (levelling arrays, plumb lines, geodetic networks, extensometers and piezometers) throughout the dam's life.
10
Tunnels and Roads • Tunnels are classified by purpose (traffic, water conveyance, sewer, mining) and by method: drill and blast (the usual method in the hard rock of Nepal), road-header and mechanical excavation, TBM, cut-and-cover for shallow depths, and immersed tube under water.
11
Support is by rock bolts, shotcrete, steel ribs and a concrete lining, adjusted by the observed convergence (NATM) — see 9.3. • Roads: the cross-section comprises the carriageway, shoulders, camber, kerbs, side drains, cut and fill slopes, formation (subgrade) and the pavement layers — subgrade, sub-base, base course and surface course.
12
Pavements are flexible (bituminous, distributing load through the layers) or rigid (cement concrete slab, acting in flexure). • Geometric design elements are the design speed, horizontal and vertical alignment, gradient (ruling, limiting and exceptional), camber, superelevation, extra widening, sight distance and the right of way.
13
In Nepal these follow the Nepal Road Standard and the Department of Roads' design guidelines, with hill roads designed to much tighter radii and steeper gradients than plains roads. • Survey inputs: centre-line survey and chainage, longitudinal profile and cross-sections at 20-50 m (closer in hills and at structures), setting out of curves, formation levels by grade stakes and sight rails, cross-slope checks and earthwork quantities.
14
Introduction • Stakeout (setting out, layout) is the reverse of surveying: instead of determining the position of existing features, it marks on the ground the position, line, level and grade of a designed feature so that construction can follow it.
15
The marks are pegs, stakes, nails, profile boards or paint, referenced to the control framework. • Principles: always set out from established control, never from another setting-out point; work from the whole to the part; check every point independently by a different method or from a different station; record everything; and protect and periodically re-check the reference marks, which are frequently disturbed on a construction site. • Tolerances are specified by the contract and are far tighter than mapping accuracies — millimetres for steel structures and machine foundations, a few millimetres to a centimetre for concrete work, centimetres for earthwork.
16
Stakeout Survey Techniques Technique Description and use Polar (bearing and distance) The standard total-station method: compute the bearing and distance from a control point to the design point and set it out directly; most instruments do this from uploaded coordinates Coordinate stake-out by total station or GNSS RTK Design coordinates uploaded and the instrument guides the rodman to the point; fast, needs no intervisibility along the works for GNSS Intersection (angular) Two or more theodolites/total stations intersect the point — used where distance cannot be measured, as for bridge piers in water Offsets from a baseline / centre line Simple tape method for buildings, roads and pipelines; right angles by the 3-4-5 rule, optical square or cross staff Profile boards, batter boards and sight rails with boning rods Wooden rails set at a known level outside the excavation; the required invert or formation level is obtained by sighting across successive rails with a traveller (boning rod) — the classic method for trenches and pipelines Grade stakes and slope (batter) stakes Mark the formation level and the point where the design side slope meets the natural ground (the catch point) in earthwork Laser level / pipe laser / rotating laser Provides a continuous reference plane or line and grade; widely used for floors, drainage and pipe laying Machine guidance (3-D) GNSS or total-station control of the blade or bucket of excavators and graders directly from the design model • Setting out a building: establish the baseline from the boundary or control, set out the main grid of column/wall centre lines, check the diagonals of every rectangle (the standard check that corners are square), transfer the lines to profile boards clear of the excavation, and mark the levels of foundation and plinth from a TBM. • Setting out a road or pipeline: peg the centre line at regular chainages and at curve points, place reference pegs offset from the centre line so that they survive excavation, set slope stakes at the catch points, and control the formation with grade stakes or sight rails. • Common errors: using an unchecked or disturbed reference mark, mixing datums or grids, transcription errors in coordinates or levels, neglecting the scale factor between grid and ground distance, and failing to check independently — the last being the cause of most serious setting-out failures.