Chapter 10
A0 (largest, 841Γ1189 mm) β A1 β A2 β A3 β A4 (210Γ297 mm, most common). Each smaller size is exactly half the area of the previous (fold an A0 in half to get A1, etc.).1:1 = full size (drawing equals object). 1:2 = reducing scale (drawing is half the object β object is larger). 2:1 = enlarging scale (drawing is twice the object β object is smaller, e.g., microchip).Continuous thick lines = visible edges and outlines. Dashed/hidden lines = edges hidden from the current view. Chain lines (dash-dot) = centre lines and axes of symmetry. Dimension lines = show the measured extent of a feature with arrowheads and figures.First-angle projection (used in Nepal, Europe, India): the object is between the viewer and the projection plane. Third-angle projection (used in USA, Canada): the projection plane is between the viewer and the object.Simple interest = PΒ·iΒ·n (P = principal, i = interest rate, n = periods). Compound interest future value: F = P(1 + i)βΏ β interest earns interest; grows exponentially.Decision rule: Accept if NPV > 0 (benefits exceed costs in present value terms); reject if NPV < 0. NPV = 0 means just break even.Decision rule: Accept if IRR > MARR. MARR (Minimum Acceptable Rate of Return) β the minimum return a project must earn (the 'hurdle rate'); set by management based on cost of capital and risk.Straight-Line (SL) = (Cost β Salvage value) / Useful life β equal annual depreciation. Declining Balance (DB) = fixed rate Γ book value β more depreciation early. Sum-of-Years-Digits (SYD) β accelerated depreciation.Initiation (define the project, feasibility) β Planning (scope, schedule, cost, risk) β Execution (carry out the work) β Monitoring & Controlling (track progress, manage changes) β Closure (formal completion, lessons learned).Critical Path β the longest path through the network, which determines the minimum project duration. Activities on the critical path have zero float (slack).Optimistic (O) β best case, Most Likely (M) β expected case, Pessimistic (P) β worst case. PERT expected time = (O + 4M + P) / 6 (weighted average, weighting most-likely Γ 4). Useful when activity durations are uncertain.Scope (what the project delivers) + Time/Schedule (when it will be done) + Cost/Budget (how much it will cost) β with Quality at the centre. Changing one constraint typically affects the others. The project manager must balance all three.Identify (find potential risks β risk register) β Analyse (qualitative: probability Γ impact matrix; quantitative: expected monetary value) β Respond (strategies: Avoid β eliminate the risk; Transfer β shift to another party e.g. insurance; Mitigate β reduce probability/impact; Accept β acknowledge and deal with if it occurs) β Monitor (track risks throughout project).Notice/Advertisement β Document Issue β Bid Preparation & Submission β Evaluation β Award.Lump-sum (Fixed Price) β contractor paid a fixed total price regardless of actual costs (contractor bears cost risk). Unit-Rate (Item-Rate) β paid per unit of completed work (e.g., per metre of road). Cost-Plus β contractor reimbursed for actual costs plus an agreed fee or percentage (client bears cost risk).Equity (owner's own funds), Debt (loans/bonds), Grants/Aid (government or international). Financial modelling determines project viability.Hold public safety, health, and welfare PARAMOUNT (the highest obligation). Act with honesty, integrity, competence, and objectivity. Practise only within your area of competence. Avoid conflicts of interest. Maintain confidentiality. Avoid bribery and corruption. Give proper credit (do not take credit for others' work).Professional Engineer (PE) or Registered Engineer licence after the candidate passes the NEC examination and fulfils experience requirements.