1
This section covers the classification and layout of hydroelectric power plants, site selection criteria, the major types of water turbines and their applications, turbine governing, and the auxiliary systems that support hydro- plant operation.
2
Classification & Layout Classification Basis Types Head available Low head (<30 m, high flow, e.g.
3
Kaplan turbines), medium head (30-300 m, e.g.
4
Francis), high head (>300 m, e.g.
5
Pelton) Water flow/storage Run-of-river (little/no storage, depends on natural river flow), storage (reservoir) type (dam impounds water for regulated release), pumped storage (water pumped back to upper reservoir during off-peak for later regeneration) Load served Base load plants (continuous, steady output) and peak load plants (quick-starting, meet demand peaks, often pondage/pumped-storage type) A typical layout comprises: intake → headrace (canal/tunnel carrying water to the forebay) → forebay/surge tank (absorbs pressure surges from load changes) → penstock (pressure pipe delivering water to the turbine) → powerhouse (turbine-generator units) → tailrace (returns water to the river downstream).
6
Site Selection Key considerations: adequate and dependable water supply/head, suitable geology/foundation conditions for dam and powerhouse, minimal environmental/social/resettlement impact, reasonable access for construction and transmission, and economic proximity to load centers.
7
Water Turbines Turbine Type & Application Pelton wheel Impulse turbine; used for high head (>300 m), low flow sites; water strikes spoon-shaped buckets via one or more jets at atmospheric pressure Francis turbine Reaction turbine; used for medium head (30-300 m), medium-high flow sites; most widely used turbine type worldwide, water flows radially inward through guide vanes onto the runner Kaplan turbine Reaction turbine (propeller-type with adjustable blades); used for low head (<30 m), high flow sites; blade pitch can be varied for efficiency across a range of flows Governing & Hydro-Plant Auxiliaries Governing of water turbines: a governor automatically regulates water flow to the turbine (via guide vanes/needle valves) to maintain constant speed (and hence frequency) as electrical load varies, preventing over-speed on sudden load rejection.
8
Hydro-plant auxiliaries include: cooling water systems, drainage and dewatering pumps, compressed air systems (for braking/governor operation), lubrication systems, cranes for maintenance, and protection/control equipment.